Retention of title in construction
Typically on construction projects, goods, materials or plant are not paid for until after they have been delivered to site. Even then, the contractual chain may mean that the client pays the main contractor at agreed intervals, and then the main contractor pays sub-contractors and so on.
This can put the supplier at risk, if the buyer (typically the contractor) defaults or becomes insolvent before payment is received. If the contractor has delivered the items and the client has received them in good faith then ownership may be disputed even if the supplier has not been paid in full.
A ‘retention of title’ clause (‘RoT, ‘Romalpa clause’ or ‘reservation of title clause’) allows a supplier to retain ownership of until specified conditions have been met, for example, until payment has been made. This is permitted under the Sale of Goods Act or the Supply of Goods and Services Act which provide that title passes from the seller to the buyer when the parties intend it to, which can be, for example; upon delivery, upon payment or upon use. This can override the general principle that title passes on delivery and can give an unpaid supplier’s title priority over the client’s.
Such clauses need to be clearly worded, it must be established that they prevail over other documentation (such as purchase orders), and they must be drawn to the attention of the contractor and client by the supplier. If the contractor becomes insolvent, or seems likely to become insolvent, the supplier should act quickly to establish their case, giving notice of retention of title, and making clear that payment has not been made.
However, even when properly prepared, retention of tile clauses can be difficult to enforce, as generally, title passes to the client once items are incorporated into the development anyway, irrespective of whether payment has been made, and it can be difficult to establish whether payment has been made, as the client may make stage payments rather than paying in total for specific items.
Other measures a supplier might take to reduce their risk include:
- Checking the financial status of the contractor to assess the likelihood of insolvency before accepting an order.
- Arranging for items to be marked and stored separately to make clear title remains with the supplier.
- Entering into a direct contract with the client.
- Seeking advance payment.
Advance payment can be secured with an advance payment bond and the client’s title established with a vesting certificate, although vesting certificates can be similarly difficult to enforce.
NB: The term ‘Romalpa clause’ refers to the case of Aluminium Industrie Vaassen BV v Romalpa Aluminium (1976) which established the principle of extended reservation of title.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Materials on site.
- Off site goods and materials.
- Off-site goods and materials - legal issues.
- Owner.
- Parent company guarantee.
- Retention.
- Vesting certificate.
[edit] External references
- BIS, Retention of title.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February